State of Kansas

Department of Transportation

Notice to Contractors

Electronic copies of the letting proposals and plans are available on the Kansas Department of Transportation (KDOT) website at https://kdotapp.ksdot.org/Proposal/Proposal.aspx. The website will allow the contractor to request approval from KDOT to bid as a prime contractor and be included on the “Bid Holders List,” or to be included on the “Non-Bid Holders List” as a subcontractor/supplier. KDOT’s approval is required to bid as a prime contractor. To bid as a prime contractor, KDOT needs to be notified of the intent to bid no later than the close of business on the Monday preceding the scheduled letting date. Failure to obtain prior approval to bid as a prime contractor on any projects listed below will be reason to reject your bid. The Secretary reserves the right to reject bids that do not comply with all requirements for preparing a bidding proposal as specified in the 2015 edition of the Kansas Department of Transportation Standard Specifications for State Road and Bridge Construction.

KDOT will only accept electronic internet proposals using the Bid Express website at https://bidx.com/ks/main until 1:00 p.m. (Central Time) on letting day. The KDOT bid letting will be conducted remotely by audio broadcast only at 3:00 p.m. (Central Time) on letting day.For the conference call information see https://www.ksdot.org/bureaus/burconsmain/lettinginfo.asp. KDOT has tested the process, but in the event of an unforeseen issue, KDOT will provide updates.

Each bidder shall certify that such person, firm, association, or corporation has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with the submitted bid. This certification shall be in the form of a required contract provision provided by the state to each prospective bidder. Failure to complete the required contract provision and certify the completeness of the preceding statement when electronically signing the proposal will make the bid nonresponsive and not eligible for award consideration.

District One – Northeast

Doniphan: 238-22 KA-7101-01 – K-238, from the US-36/K-238 junction north to the Kansas/Nebraska state line, milling and overlay, 1.4 miles. (State Funds)

Douglas: 10-23 KA-6977-01 – K-10, slopes at the intersection of Peach Orchard Road (1900 Road) and K-10, slide repair. (State Funds)

Jackson: 214-43 KA-7099-01 – K-214, from the US-75/K-214 south junction north to US-75/K-214 north junction, sealing, 2.0 miles. (State Funds)

Jefferson: 16-44 KA-7042-01 – K-16, from the US-59/K-16 south junction east to the west city limits of McLouth, milling and overlay, 5.6 miles. (Federal Funds)

Lyon: 35 56 KA-7142-01 – I-35, from 0.09 mile north of the I-35/KTA junction north to the I-35/US-50 east junction, pavement marking, 5.8 miles. (Federal Funds)

Nemaha: 36-66 KA-3880-01 – US-36, bridge #001 over the North Fork Black Vermillion River located 1.06 miles east of the Nemaha/Marshall County line, bridge replacement. (Federal Funds)

Riley: 18-81 KA-5469-01 – K-18, beginning at the K-18/K-177 west junction, east to 0.10 mile east of the K-18/K-177 east junction, pavement reconstruction, 0.7 mile. (Federal Funds)

Shawnee: 70-89 KA-7143-01 – I-70, from 1.6 miles east of the I-70/K-4 junction east to MacVicar; from 0.11 mile east of Adams Street east to 0.12 mile east of the I-470/I-70/US-40/K-4 junction, pavement marking, 8.2 miles. (Federal Funds)

Wyandotte: 105 N-0728-01 – 98th Street, in Edwardsville from Kansas Avenue to the north city limits, grading and surfacing, 1.0 mile. (Federal Funds)

District Two – North Central

Ellsworth: 156-27 KA-7103-01 – K-156, from the north city limits of Ellsworth northeast to I-70/K-156 junction, milling and overlay, 10.7 miles. (Federal Funds)

Lincoln: 53-C 5120-01 – Lincoln County, all paved major collectors, minor collectors and local roads, pavement marking, 25.7 miles. (Federal Funds)

McPherson: 135-59 KA-6752-01 – I-135, bridge #032 and bridge #033 over the KO Railroad located 0.76 mile north of US-56 (northbound and southbound), bridge repair. (State Funds)

District Three – Northwest

Ellis: 255-26 KA-7104-01 – K-255, from the beginning of route north to I-70/K-255 junction, milling and overlay, 1.2 miles. (State Funds)

Graham: 283-33 KA-7105-01 – US-283, from 2.7 miles north of the Graham/Trego County line north to the US-24/US-283 junction, sealing, 13.7 miles. (Federal Funds)

Phillips: 74-C 5130-01 – Phillips County, all major collectors, minor collectors and local roads west of US-183, signing, 156 miles. (Federal Funds)

Rawlins: 36-77 KA-5987-01 – US-36, in Atwood from 5th Street to 7th Street, grading and surfacing, 0.1 mile. (Federal Funds)

District Four – Southeast

Bourbon: 54-6 KA-6884-01 – US-54, light tower #1: 006L0002 located east of US-69 approximately 500 feet south of US-54; light tower #2: 006L0003 located west of US-69 approximately 750 feet north of US-54; light tower #3: 006L0001 located south of US-54 approximately 500 feet west of US-69, lighting, 0.5 mile. (State Funds)

Cherokee: 11 C-5153-01 – Bridge, 0.5 mile south and 0.8 mile east of Columbus over Brush Creek, bridge replacement, 0.1 mile. (Federal Funds)

Coffey: 75-16 KA-7090-01 – US-75, from the Woodson/Coffey County line north to the south edge wearing surface of bridge #056 over North Big Creek located north of the K-58 north junction, milling and overlay, 4.0 miles. (Federal Funds)

Coffey: 35-16 KA-6901-01 – I-35, bridge #013 over US-75 located 12.32 miles east of the Lyon County line, bridge repair. (State Funds)

Montgomery: 63 C-5128-01 – County Road 4700 (portions of RS 1673 and RS 507), from 126 feet south of CR 1450 to Coffeyville south city limit, grading and surfacing, 1.1 miles. (Federal Funds)

Wilson: 75-103 KA-7098-01 – US-75, from the east city limits of Neodesha north to the Wilson/Woodson County line, sealing, 23.9 miles. (State Funds)

Woodson: 75-104 KA-7089-01 – US-75, from the north city limits of Yates Center north to the Woodson/Coffey County line, milling and overlay, 10.5 miles. (Federal Funds)

Statewide: 106 TE-0402-07 – Flint Hills Trail, Iowa Road to Louisiana Terrace west of the city of Ottawa in Franklin County, special, 2.3 miles. (Federal Funds)

District Five – South Central

Butler: 8 KA-7044-01 – US-54, bridge #005 over Whitewater River located 0.7 mile east of Southwest River Valley Road; K-254, bridge #165 over Whitewater River located 0.7 mile east of Southwest River Valley Road, bridge repair. (State Funds)

Comanche: 17 C-5129-01 – Intersection of RS 711 and RS 963, intersection improvement, 1.0 mile. (Federal Funds)

Cowley: 166-18 KA-7092-01 – US-166, from the Sumner/Cowley County line east to the west city limits of Arkansas City, milling and overlay, 5.0 miles. (Federal Funds)

Harvey: 135-40 KA-6938-01 – Culvert #532 over Sand Creek drainage, culvert repair, 0.01 mile. (State Funds)

Kiowa: 54-49 KA-5783-01 – US-54, from 6.8 miles east of the US-54/US-183 junction east for 0.43 mile (westerly extension) and 8.4 miles east of the US-54/US-183 junction east for 0.76 mile (easterly extension), including widening of bridge #519, grading and surfacing, 1.2 miles. (Federal Funds)

Kiowa: 54-49 KA-5785 01 – US-54, from 1 mile east of the Ford/Kiowa county line east for 1.95 miles, grading and surfacing, 2.0 miles. (Federal Funds)

Pawnee: 19-73 KA-7093-01 – K-19 Spur, from the K-19/K-19 Spur junction north to the US-56/K-19 Spur junction; K-19, from the K-19/K-19 Spur junction east to the Pawnee/Stafford County line, milling and overlay, 10.6 miles. (Federal Funds)

Rice: 14-80 KA-7041-01 – K-14, from 0.26 mile north of Avenue U north to the south city limits of Lyons, milling and overlay, 7.1 miles. (Federal Funds)

Stafford: 19-93 KA-7094-01 – K-19, from the Pawnee/Stafford County line east to US-281/K-19 junction, milling and overlay, 9.0 miles. (Federal Funds)

Sumner: 166-96 KA-7091-01 – US-166, from mile marker 9 east to the Sumner/Cowley County line, milling and overlay, 5.0 miles. (Federal Funds)

District Six – Southwest

Finney: 156-28 KA-6440-01 – K-156, from 130 feet east of 3rd/4th Street east to 300 feet west of Belmont Place, grading and surfacing, 0.2 mile. (Federal Funds)

Meade: 54-60 KA-5782 01 – US-54, from 3.4 miles east of the east US-54/US-160 junction east for 2.7 miles, grading and surfacing, 2.7 miles. (Federal Funds)

Meade: 54-60 KA-5781-01 – US-54, from the Meade/Seward County line east for 1.8 miles, grading and surfacing, 1.8 miles. (Federal Funds)

Greg Schieber
State Transportation Engineer
Acting Secretary

Doc. No. 051342