Department of Transportation

Notice to Contractors

Electronic copies of the letting proposals and plans are available on the Kansas Department of Transportation (KDOT) website at https://kdotapp.ksdot.org/Proposal/Proposal.aspx. The website will allow the contractor to request approval from KDOT to bid as a prime contractor and be included on the “Bid Holders List,” or to be included on the “Non-Bid Holders List” as a subcontractor/supplier. KDOT’s approval is required to bid as a prime contractor. To bid as a prime contractor, KDOT needs to be notified of the intent to bid no later than the close of business on the Monday preceding the scheduled letting date. Failure to obtain prior approval to bid as a prime contractor on any projects listed below will be reason to reject your bid. The Secretary reserves the right to reject bids that do not comply with all requirements for preparing a bidding proposal as specified in the 2015 edition of the Kansas Department of Transportation Standard Specifications for State Road and Bridge Construction.

KDOT will only accept electronic Internet proposals using the Bid Express website at https://bidx.com/ks/main until 1:00 p.m. (Central Time) on letting day. The KDOT bid letting will be conducted remotely by audio broadcast only at 3:00 p.m. (Central Time) on letting day. For the conference call information see https://www.ksdot.org/bureaus/burconsmain/lettinginfo.asp. KDOT has tested the process, but in the event of an unforeseen issue, KDOT will provide updates.

Each bidder shall certify that such person, firm, association, or corporation has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with the submitted bid. This certification shall be in the form of a required contract provision provided by the state to each prospective bidder. Failure to complete the required contract provision and certify the completeness of the preceding statement when electronically signing the proposal will make the bid nonresponsive and not eligible for award consideration.

Projects for the April 16, 2025 Letting

District One – Northeast

Shawnee: 24-89 KA-7359-01 – US-24, bridge #248 over Cross Creek located 5.1 miles southeast of the Shawnee/Pottawatomie County line, bridge repair. (State Funds)

Wabaunsee: 70-99 KA-7607-01 – I-70, bridge #006 carrying I-70 westbound over Pretty Creek located 1.04 miles east of the K-99 junction, bridge repair. (Federal Funds)

Wyandotte: 635-105 KA-7191-02 – I-635, from the north approach of bridges #040 and #041 over the BNSF Railroad Yard and K-32 north to 1.36 miles north of I-70/I-635 junction, guard fence, 2.4 miles. (State Funds)

Statewide: 106 KA-7258-01 – Routes US-75, K-62, K-79, K-16 and K-116 in Jackson, Shawnee, Nemaha, Pottawatomie, Atchison, and Jefferson Counties, signing. (State Funds)

District Two – North Central

Ellsworth: 70-27 KA-7551-01 – I-70, from the Russell/Ellsworth County line east to the Ellsworth/Lincoln County line, pavement patching, 23.3 miles. (Federal Funds)

Geary: 70-31 KA-6483-01 – I-70, bridge #016 over I-70 at J. Hill Road located 2.37 miles east of the US-40B west junction, bridge replacement. (Federal Funds)

Lincoln: 70-53 KA-7552-01 – I-70, from the Ellsworth/Lincoln County line east to the Lincoln/Saline County line, pavement patching, 7.2 miles. (Federal Funds)

McPherson: 61-59 KA-7612-01 – K-61, bridge #099 carrying northbound K-61 over K-153 spur/old US-81 located at the K-61/K-153 spur junction, bridge repair. (Federal Funds)

McPherson: 135-59 KA-6063-02 – I-135, from the Harvey/McPherson County line north to 6.3 miles north of the Harvey/McPherson County line, guard fence, 6.3 miles. (State Funds)

Mitchell: 14-62 KA-6972-01 – K-14, bridge #029 Solomon River located 2.19 miles south of US-24 in Beloit, bridge repair. (State Funds)

Morris: 64 C-5260-01 – Remaining 97 miles of major and minor collectors not signed as part of C-4900-01, signing, 97.0 miles. (Federal Funds)

Saline: 4-85 KA-3230-02 – K-4, from bridge #144 over Smoky Hill River east to 0.3 miles east of the K-4/South Kipp Road intersection (2.23 miles east of the K-4/K-104 junction), grading, bridge and surfacing, 7.1 miles. (Federal Funds)

Washington: 101 C-5296-01 – Washington county, bridge over Little Blue River Tributary on West Washington Street located in Hanover, bridge replacement, 0.1 miles. (Federal Funds)

Statewide: 135-106 KA-7202-01 – Bridge approaches from Limestone Road north to 8.41 miles north of US-56 on I-135, includes bridges #040 and #041 located 5.4 miles north of the I-135/US-56 junction in McPherson County and bridges #148 and #149 located at the I-135/US-81/K-4 south junction in Saline County, milling and overlay, 8.0 miles. (State Funds)

District Three – Northwest

Russell: 70-84 KA-7144-02 – I-70 crossroad pipe, located 0.57 miles east of 178th Street, special. (State Funds)

Statewide: 106 KA-7284-01 – Routes US-83, K-25 and US-40 in Logan and Thomas counties, signing. (State Funds)

District Four – Southeast

Bourbon: 6 C-5286-01 – Bridge over Tributary to Hinton Creek, located 5.9 miles south and 1.0 miles west of Uniontown, bridge replacement, 0.2 miles. (Federal Funds)

Franklin: 30 C-5284-01 – Bridge over Walnut Creek, located 1.0 miles east and 3.4 miles south of Le Loup, bridge replacement, 0.2 miles. (Federal Funds)

Greenwood: 400-37 KA-7670-01 – US-400, from K-99/US-400 east junction east to the Greenwood/Wilson County line, crack repair, 15.2 miles. (State Funds)

Statewide: 106 KA-7278-01 – Routes US-69, K-152, K-3, K-31, K-7, K-52 and K-239 in Linn, Miami, Anderson and Bourbon counties, signing. (State Funds)

District Five – South Central

Statewide: 106 KA-7285-01 – Routes US-281, K-8, K-2 and US-160 in Barber, Pratt, Comanche, and Harper Counties, signing. (State Funds)

Calvin Reed