Request for Proposals

Notice to Consulting Firms

The Kansas Department of Transportation (KDOT) is seeking a qualified consulting firm, or team of firms, to perform construction inspection services on multiple projects in various counties. Summary information for each project is provided below in Table 1.

Interested consultants must upload a proposal by 12:00 p.m. (Central Time) February 26, 2025, to the Bid Express page to be considered for selection.

Consultant Prequalification

Interested consulting firms must be prequalified by KDOT or otherwise demonstrate qualification in the following category(s):

  • 241 – Construction Inspection and Testing

If a firm is not currently prequalified by KDOT, a proposal may still be submitted. Firms not prequalified must also provide documentation that demonstrates the firm is qualified for each specified category listed in this notice for the project. Firms must use the KDOT prequalification form to provide this documentation. KDOT 1050 Prequalification Category Definitions (Blue Book) can be found at http://www.ksdot.org/descons.asp. Consultants may create a team to meet the prequalification requirements. All firms doing business with KDOT must be registered and in good standing under the laws of the State of Kansas at the time of contracting and must comply with applicable state and federal laws, rules, and regulations.

Background and Scope of Projects

With this single solicitation, KDOT is requesting consulting services for construction inspections on the projects listed in Table 1. This table provides summary information for each project. One consultant will be selected to perform services associated with each group listed. Firms can express interest in the groups for which they would like to be considered by submitting a response as indicated below. There is no guarantee that a firm which has expressed interest will be selected for any project(s).

Table 1: Summary of Project Information
Group RT-CO Project # Scope, County Anticipated Start Working Days or CCD Office
24422 U075-103 KA-6782-01 Grading, Bridge, and Surfacing,
Wilson
April 14, 2025 235 Independence
24423 U160-063 KA-6958-01 Bridge Repair,
Montgomery
April 7, 2025 160 Independence
25101 -106 KA-7454-01 Continuously Operating Reference Station (CORS)
Multiple
March 15, 2025 55
25102 -106 KA-7238-01 Sidewalk Improvements,
Multiple
March 15, 2025 65 Bonner Springs
25103 U077-058 KA-7503-01 Resurfacing,
Marshall
60 Wamego
K009-058 KA-7502-01 Resurfacing,
Marshall
60
K099-058 KA-7544-01 Resurfacing,
Marshall
40
U036-058 KA-7566-01 Resurfacing,
Marshall
40
25104 K005-105 KA-7472-01 Resurfacing,
Wyandotte
45 Bonner Springs
K016-106 KA-7469-01 Resurfacing,
Multiple
April 14, 2025 50
25105 U024-023 KA-7512-01 Resurfacing,
Douglas
95 Bonner Springs
U059-044 KA-7513-01 Resurfacing,
Jefferson
95
U024-044 KA-7510-01 Resurfacing,
Jefferson
95
25106 I670-105 KA-7549-01 Resurfacing,
Wyandotte
September 25, 2026 Bonner Springs
I670-105 KA-7550-01 Resurfacing,
Wyandotte
September 25, 2026
25107 I070-105 KA-7548-01 Resurfacing,
Wyandotte
September 21, 2025 Bonner Springs
25201 U081-079 KA-7374-01 Resurfacing,
Republic
35 Belleville
-106 KA-7401-01 Resurfacing
Multiple
35
25202 U036-079 KA-7382-01 Resurfacing,
Republic
May 5, 2025 45 Belleville
25301 K027-091 KA-6123-01 Bridge Repair,
Sherman
June 2, 2025 95 Atwood
25302 K027-100 KA-6778-01 Bridge Repair,
Wallace
May 1, 2025 October 31, 2025 Oakley
25303 K023-090 KA-5756-01 Grading, Bridge, and Surfacing,
Sheridan
July 1, 2025 210 Oakley
25304 I070-097 KA-7445-01 Resurfacing,
Thomas
March 24, 2025 80 Oakley
25401 K007-006 KA-5804-01 Grading, Bridge, and Surfacing,
Bourbon
June 18, 2027 Iola
K007-019 KA-5803-02 Grading, Bridge, and Surfacing,
Crawford
June 18, 2027 Pittsburg
25402 U169-01 KA-7484-01 Resurfacing,
Miami
55 Garnett
K279-061 KA-7485-01 Resurfacing,
Miami
55
25403 U069-054 KA-7543-01 Resurfacing,
Linn
35 Garnett
25501 U050-040 KA-7460-01 Resurfacing,
Harvey
March 31, 2025 35 El Dorado/Hutchinson
25502 U077-008 KA-7456-01 Resurfacing,
Butler
May 5, 2025 35 El Dorado/Hutchinson
25503 U281-004 KA-7430-01 Resurfacing,
Barber
June 2, 2025 50 Pratt
U160-004 KA-7429-01 Resurfacing,
Barber
June 2, 2025 45

Additional project information including construction scope to be inspected, a detailed description of the project location, and resources and inspection scope specifically requested from consultants in this request can be viewed in an online table at https://ike.ksdot.gov/about/construction-inspection-rfps. Upon publication of this Request for Proposals, KDOT anticipates each of these inspection efforts will require full teams (project manager and inspectors, as opposed to single role staff augmentation as is occasionally request) for various types of construction inspection except as noted in the table. Watch the website linked above for updated information. Tabulated information (both in this Request for Proposals and on the website) shall not be relied upon during inspections. It is provided for the convenience of consultants, specifically to aid in making decisions about which projects they are interested in performing.

Specific project needs are subject to modification and/or cancellation at KDOT’s discretion.

Anticipated Consultant Scope

The scope of construction inspection services and certifications required will vary for each project and are listed in the table available on the website noted above. Inspection efforts will be managed out of the offices listed. Also included for the convenience of consultants are indications of which grouped projects are currently slated to be performed by the same contractors.

Anticipated Schedule and Key Dates

  1. Proposals are due by or before 12:00 p.m. (Central Time) February 26, 2025.
  2. Ranking of proposals is expected to occur on or around February 28, 2025. Negotiations with the most highly ranked firm are expected to begin on or around March 7, 2025. An executed agreement is anticipated shortly thereafter.
  3. Anticipated scope starts dates and working days or anticipated calendar completion dates are shown in the table. All dates are subject to change.

Instructions for Proposal

  1. No cost or pricing information shall be submitted with the proposal. Proposals including cost or pricing information will be considered non-responsive and withdrawn from further consideration.
  2. The consultant’s proposal must not exceed the page limit laid out in Table 2 below (including any cover letter, index, etc.). All pages shall be standard letter size (8.5” x 11”). Any page larger than standard letter size will be counted as two or more pages depending on size.
  3. A single PDF (10MB maximum size) of the proposal including all attachments must be uploaded to the appropriate bid form on Bid Express by the proposal due date and time.
  4. The proposal PDF file name must read:
    1. “ConstInsp Multiple Projects_2025.02 Release FIRM NAME”
  5. The proposal must be accompanied by Special Attachments No. 8 (“Tax Clearance Certificate”), No. 10 (“Policy Regarding Sexual Harassment”), and No. 12 (“Certification of Company Not Currently Engaged in the Procurement or Obtainment of Certain Equipment, Services, or Systems”). If you need a Tax Clearance Certificate, you can request one https://www.ksrevenue.gov/taxclearance.html. Allow 2-3 business days for processing. All attachments are required for every firm involved in a multi-consultant team. Upload these files as instructed in Bid Express.
  6. The outline in Table 2 below describes the expected proposal organization, content sections, and limits on number of pages.
    1. Each team is limited to a single, one-page cover letter.
    2. Consultants may indicate interest in any and all projects, indicate preference (s) for up to three projects, and shall both indicate interest and preferences on the “June 2024 Construction Inspections Interest & Preference Form is provided on the Bid Express page to complete and upload. Also, consultants are to use the bottom of that form to indicate any capacity limitations that need to be taken into account when making selections.
    3. Thereafter, each team is limited to two pages per project in which they express interest. In these pages, consultants shall:
      1. Describe the approach they plan to execute to deliver success on the project.
      2. Present the relevant qualifications and experience of the people they are proposing will provide the services.
      3. Provide the firm’s familiarity with KDOT and the project area.
    4. Finally, consultants are limited to a single, on-page descriptions of general qualifications (“Past Performance” selection plus “Approach to Quality Control” section) regardless of the number of projects in which they are expressing interest.
  7. Table 3 lists the evaluation criteria and associated weights which will be used to make a selection.
  8. Although not anticipated at this time, KDOT reserves the right to interview for the requested services associated with any of the listed projects prior to making final selections.
Table 2: Proposal Content
Section Description of Intent Page Limit
Cover Letter 1 Page
Consultant Project Interest and Preference Fill out “February 2025 Construction Inspections Interest & Preference Form” and submit with your proposal. 1 Page
Project Approach Describe how your firm will meet the fluctuating inspection needs of the project. 2 Pages
per project in which team is interested
Qualifications and Experience For key personnel to be assigned to the project provide names, qualifications, education, training, and expertise. Identify their area(s) of responsibility and percent of their time dedicated to the project. List work for which you do not have in-house capability and name the firm you propose to subcontract with.
Familiarity with KDOT and Project Area Describe team’s familiarity with KDOT’s inspection processes and standards. Describe familiarity with the project area and any identified special site conditions.
Past Performance Describe team’s past performance with respect to ability to meet project schedules; quality of work; and ability to control costs on similar transportation projects, especially those performed for KDOT. Include three references and contact information. 1 Page
total
Approach to Quality Control Describe methods or procedures your firm will use to provide all services with professional quality and technical accuracy.
Table 3: Evaluation Factors
Evaluation Factor Weight
The quality and completeness of the response 10%
Availability to respond to the work 20%
Qualifications and experience of project manager and other key project team members proposed for services 20%
Past performance history for similar projects/services for KDOT 20%
Understanding of the project area 10%
Understanding of KDOT contract administration and closeout procedures 20%

Contract Terms and Conditions

A standard KDOT agreement for engineering and technical services will be used for professional services projects. The following special attachments will need to be provided by the selected consultant and all subconsultants with the signed work order following negotiations and will become attachments to the contract.

  • Special Attachment No. 8 (“Tax Clearance Certificate”)
  • Special Attachment No. 10 (“Policy Regarding Sexual Harassment”)
  • Special Attachment No. 12 (“Certification of Company Not Currently Engaged in the Procurement or Obtainment of Certain Equipment, Services, or Systems”)

Special Contract Conditions

Batch Request for Proposals.

Questions

All questions regarding this Request for Proposals shall be submitted via Q&A section of bid form in Bid Express.

Questions can be submitted until February 12, 2025; answers will be provided to all prequalified consultants on February 19, 2025.

Calvin Reed
Secretary
Department of Transportation

Doc. No. 052850