Notice to Consulting Firms

The Kansas Department of Transportation (KDOT) is seeking a qualified consulting firm or team of firms to perform professional services for the project(s) described in Table 1 below. Interested consultants must email a proposal to KDOT.DesignContracts@ks.gov by 12:00 p.m. (CDT) August 10, 2022, to be considered for selection.

Consultant Prequalification

Interested consulting firms must be pre-qualified by KDOT or otherwise demonstrate qualification in category(s):

  • 201 Location and Design Concept Studies/Corridor Studies
  • 211 Highway Design–Major Facility
  • 231 Traffic Control Analysis and Design
  • 301 Land Surveying
  • 302 Engineering Surveying
  • 336 Right of Way Services
  • 401 Landscape Seeding and Erosion Control

If a firm is not currently prequalified by KDOT, a proposal may still be submitted. Firms not prequalified must also provide documentation that demonstrates the firm is qualified for each specified category listed in this notice for the project. Firms must use the KDOT prequalification form to provide this documentation. KDOT 1050 Prequalification Category Definitions (Blue Book) can be found at http://www.ksdot.org/descons.asp. Consultants may create a team to meet the prequalification requirements. All firms doing business with KDOT must be registered and in good standing under the laws of the State of Kansas at the time of contracting and must comply with applicable state and federal laws, rules, and regulations.

Table 1: Background and Scope of Project
Project Number Background and Scope of Project
KA-6559-01 US-54: Discovery phase to investigate reconstruction to 4-lane with intersection improvements from US-54/US-83/E. 2nd Street/Bluebell Road in Liberal northeast to County Road 6.

Table 2: Project Summary
Project Number Route and Scope Length (mi) Project Termini
KA-6559-01 054-088
US-54 Reconstruction/Expansion to 4-lane
3.1 US-54/US-83 intersection to County Road 6 in Seward County

Anticipated Consultant Scope

KDOT anticipates the following to be included in the consultant’s scope:

Planning Study Services; Discovery Phase Services

Based on funding needs identified and developed during the Discovery Phase, the Consultant selected for this RFP may or may not continue providing services up through the Preliminary and/or Final design and Construction Engineering Services phases. Additional scope which may be added during later phases (at the Secretary’s discretion) may include Survey Services; Preliminary Design Services; Final Design Services; Pavement Design Services; Public Involvement Services; Environmental Documentation Preparation (Permitting); Geotechnical Services; Right of Way Services; Letting and Construction Phase Services; 3D Electronic; Deliverables Preparation.

Current expectations for consultant scope are detailed below. The scope included herein may not be all-inclusive. A scoping meeting will take place after consultant selection is made.

Project Management

  • Develop and communicate Project Management Plan and Quality Assurance Plan.
  • Perform quality control checks according to Quality Assurance Plan.
  • Provide electronic plan files compliant with KDOT Graphic Standards Manual, including CAD conformance checks and ControlCAD indexed DGN files with ProjectWise attributes.
  • Provide bi-annual construction cost estimates and at major project milestones.

Environmental

  • High-level data gathering.
  • Identify potential issues.
  • Subsequent phases may include:
    • Completing environmental data collecting and analysis.
    • Submitting findings.
    • Final permitting.

Road Design

  • Discovery Phase.
  • Visit the project site location.
  • Subsequent phases may include:
    • Develop plans to Materials and Research.
    • Develop Preliminary Plans to Field Check.
    • Develop Office Check Plans.
    • Perform roadway geometric design, drainage design, and roadside safety analysis.
    • Develop Final Plans for Construction.

Survey and Right of Way

  • Utilize existing LIDAR data for preliminary location survey.
  • Subsequent phases may include:
    • Provide a full survey including structures in the existing right of way. The deliverables shall incorporate the full project and will be provided in the Kansas Regional Coordinate System.
    • Establish and determine impacts to right of way and utilities.
    • Building of the existing right of way.
      • Based upon consultant’s field survey data and historical KDOT project information, consultant shall establish and compile into a right of way strip map the positions and locations of the existing highway right of way and property lines for the ownership adjacent thereto. Consultant shall perform these activities using coordinate geometry and Bentley Open Site Designer.

Traffic Engineering

  • Discovery Phase.
  • Subsequent phases may include:
    • Develop permanent signing and pavement marking plans.
    • Develop Traffic Control Plans.

Transportation Planning

  • Develop both daily and AM/PM peak hour traffic for base/future year traffic for the study area.
  • Data collection of present traffic (counts) as needed or deemed necessary. Data collection of present traffic (counts) as needed or deemed necessary.
  • Coordinate information with the Transportation Planning Forecasting Group

Activities to be performed by KDOT

Environmental services, including lead paint and asbestos testing and permit application.

Note: Technical data to support these activities will be required from the consultant immediately after field check. Utility coordination, if required. Geotechnical services including soil investigations, bridge foundation geology, pavement field investigation and design, and surfacing recommendations.

Anticipated Schedule and Key Dates

  1. Proposals are due by or before 12:00 p.m. (CDT) August 10, 2022
  2. The program fiscal year for this project is FY 2023.
  3. Other important dates:
    1. Begin Study: October 17, 2022
    2. End Study: May 19, 2023

Instructions for Proposal

  1. No cost or pricing information shall be submitted with the proposal. Proposals including cost or pricing information will be considered non-responsive and withdrawn from further consideration.
  2. The consultant’s proposal must not exceed 5 pages total (including any cover letter, index, etc.). All pages shall be standard letter size (8.5” x 11”). Any page larger than standard letter size will be count as two or more pages depending on size.
  3. A single PDF (2MB maximum size) of the proposal including all attachments must be emailed to KDOT.DesignContracts@ks.gov by the proposal due date and time.
  4. The subject line of the email and the PDF file name must read:
    1. “KA-6559-01 U-54 Discovery in Seward County _FIRM NAME”
  5. The proposal must be accompanied by Special Attachments No. 8 (“Tax Clearance Certificate”) and No. 10 (“Policy Regarding Sexual Harassment”). If you need a Tax Clearance Certificate, you can request one at https://www.ksrevenue.gov/taxclearance.html. Allow 2-3 business days for processing.
  6. The outline in Table 3 below describes the expected proposal organization and content sections.
  7. Table 4 lists the evaluation criteria and associated weights which will be used to make a selection.

Table 3: Proposal Content
Section Description of Intent
Cover Letter 1 page
Project Approach Demonstrate a unique approach to accomplish the design efficiently and to a high standard. Include cost-effective and optimized solutions to address the anticipated improvements in the design. Include unique qualifications or experience related to the project approach.
Approach to Schedule Describe the approach to accomplish the scope of services within the schedule requirements. Include anticipated key milestone dates and availability of staff.
Approach to Quality Control Describe methods or procedures your firm will use to provide all drawings, reports and other services with professional quality and technical accuracy.
Qualifications and Experience For key personnel to be assigned to the project provide names, office location, qualifications, education, training, and expertise. Identify their area(s) of responsibility and percent of their time dedicated to the project. List work for which you do not have in-house capability and name the firm you propose to subcontract with.
Past Performance Describe team’s past performance with respect to ability to meet project schedules; quality of work; and ability to control costs on similar transportation projects, especially those performed for KDOT. Include three references and contact information.
Familiarity with KDOT and Project Area Describe team’s familiarity with KDOT’s design process and standards. Describe familiarity with the project area and any identified special site conditions.

Table 4: Evaluation Factors
Evaluation Factor Weight
Qualifications and experience of project manager and other key project team members proposed for services 20%
Project approach 30%
Approach and commitment to meet advertised schedule 10%
Past performance history for similar projects/services for KDOT 10%
Understanding of the project area 10%
Approach to quality control 10%
Demonstrated understanding of nature and scope of project 10%

Contract Terms and Conditions

A standard KDOT agreement for engineering and technical services will be used for professional services projects. The following special attachments will need to be provided by the selected consultant and all subconsultants with the signed work order following negotiations and will become attachments to the contract.

  • Special Attachment No. 8 (“Tax Clearance Certificate”)
  • Special Attachment No. 10 (“Policy Regarding Sexual Harassment”)

Questions

All questions regarding this Request for Proposals shall be emailed to KDOT.DesignContracts@ks.gov.

Questions can be submitted until July 27, 2022; answers will be provided to all prequalified consultants on August 3, 2022.

Marcia Turner, P.E., Contracts Manager