Volume 41 - Issue 21 - May 26, 2022
State of Kansas
Department of Transportation
Notice to Consulting Firms
The Kansas Department of Transportation (KDOT) is seeking a qualified consulting firm or team of firms to perform professional services for the project(s) described in Table 1 below. Interested consultants must email a letter of interest to KDOT.DesignContracts@ks.gov by 12:00 p.m. (CDT) June 8, 2022, to be considered for selection.
Consultant Prequalification
Interested consulting firms must be prequalified by KDOT or otherwise demonstrate qualification in the following Categories: 161 Corridor/Project Feasibility Studies; 171 Environmental Documentation; 212 Highway Design–Minor Facility; 221 Non-Standard Span Bridge Design; 231 Traffic Control Analysis and Design; 301 Land Surveying; 302 Engineering Surveying; 336 Right of Way Services; and 401 Landscape Seeding and Erosion Control.
If a firm is not currently prequalified by KDOT, a proposal may still be submitted. Firms not prequalified must also provide documentation that demonstrates the firm is qualified for each specified category listed in this notice for the project. Firms must use the KDOT prequalification form to provide this documentation. KDOT 1050 Prequalification category definitions (Blue Book) can be found at http://www.ksdot.org/descons.asp. Consultants may create a team to meet the prequalification requirements. All firms doing business with KDOT must be registered and in good standing under the laws of the State of Kansas at the time of contracting and must comply with applicable state and federal laws, rules, and regulations.
Table 1: Background and Scope of Project | |
---|---|
Project Number | Background and Scope of Project |
KA-5731-01 | This project is the replacement of the US-24 bridge (BR#026) over Kyle Railroad, which carries traffic east and west between Cawker City in Osborne County. This structure is on a straight alignment with a 59°-19’-10” skew to the right. The length of the existing bridge is 238.9’ feet; the roadway width is 44 feet. This project is scheduled for letting in FY 2026 with plans complete November 18, 2025. |
Table 2: Project Summary | |||
---|---|---|---|
Project Number | Route and Scope | Length (mi) | Project Termini |
KA-5731-01 | 024–071 Bridge Replacement |
0.01 | N/A |
Project Number | Structures BR#, Structure Scope, Structure Size and Type | ||
KA-5731-01 | Bridge #026 Bridge Replacement, Existing structure is a skewed Illinois Bulletin bridge (RISC) approximately 238.9 feet long. Services associated with this request for proposal begin at Discovery Phase and consultant may be retained (via supplemental agreements) through Final Design. |
Anticipated Consultant Scope
KDOT anticipates the following to be included in the consultant’s scope: Current expectations for consultant scope are detailed below. The scope included herein may not be all-inclusive. A scoping meeting will take place after consultant selection is made.
Project Management
- Develop and communicate Project Management Plan and Quality Assurance Plan.
- Perform quality control checks according to Quality Assurance Plan.
- Provide electronic plan files compliant with KDOT Graphic Standards Manual, including CAD conformance checks and ControlCAD indexed DGN files with ProjectWise attributes.
- Provide bi-annual construction cost estimates and at major project milestones.
- Coordinate with required entities, including the Union Pacific Railroad, the Kyle Railroad, and the United States Bureau of Reclamation.
Environmental
- High-level data gathering.
- Identify potential issues.
- Subsequent phases may include:
- Completing environmental data collecting and analysis.
- Submitting findings.
- Final permitting.
Road Design
- Discovery Phase including NEPA (EA/EIS).
- Visit the project site location.
- Subsequent phases may include:
- Develop Plans to Materials and Research.
- Develop Preliminary Plans to Field Check.
- Develop Office Check Plans.
- Develop Final Plans for Construction.
- Perform roadway geometric design, drainage design, and roadside safety analysis.
Survey and Right of Way
- KDOT completed a full survey of the project area on April 29, 2021.
- Existing Right of Way features were completed on September 20, 2021.
- Subsequent phases may include:
- Topographic Field Survey.
- Based upon Consultant’s field survey data and historical KDOT project information, consultant shall establish and compile into a right of way strip map the positions and locations of the existing highway right of way and property lines for the ownership adjacent thereto. Consultant shall perform these activities using coordinate geometry and Bentley Open Site Designer.
Bridge Design
- Discovery Phase.
- Subsequent phases may include:
- Develop Preliminary Plans to Field Check.
- Develop Office Check Plan.
- Develop Final Plans for Construction:
- The consultant will propose and evaluate different framing layouts for review and acceptance by the KDOT Bridge Office; focus shall be to minimize disruption to the site and facilitate efficient construction to minimize impacts to US-24 and the Kyle Railroad.
Traffic Engineering
- Discovery Phase.
- Subsequent phase may include:
- Develop permanent signing, lighting, and pavement marking plans.
- Development of Traffic Management Plan, including coordination with the local government and the railroads.
- Develop Traffic Control Plans.
Activities to be performed by KDOT include:
- Environmental services, including lead paint testing and permit application.
- Note: Technical data to support these activities will be required from the consultant immediately after field check.
- Utility coordination, if required.
- Geotechnical services including soil investigations, bridge foundation geology, pavement field investigation and design, and surfacing recommendations.
Anticipated Schedule and Key Dates
- Proposals are due by or before 12:00 p.m. (CDT) June 8, 2022
- The program fiscal year for this project is FY 2026 (July 2025 – June 2026)
- Other important dates:
- Survey is complete
- Begin Study: August 15, 2022
- End Study: January 9, 2023
- Plans to Materials and Research: March 8, 2023
- Field Check: December 7, 2023
- Plans to Right-of-Way: February 21, 2024
- Plans Complete: November 18, 2025
Instructions for Proposal
- No cost or pricing information shall be submitted with the proposal. Proposals including cost or pricing information will be considered non-responsive and withdrawn from further consideration.
- The consultant’s proposal must not exceed 6 pages total (including any cover letter, index, etc.). All pages shall be standard letter size (8.5” x 11”). Any page larger than standard letter size will be count as two or more pages depending on size.
- A PDF (2MB maximum size) of the proposal must be emailed to KDOT.DesignContracts@ks.gov by the proposal due date and time.
- The subject line of the email and the PDF file name must read:
- “KA-5731-01–Replace BR026 over Kyle RR in Osborne Co_FIRM NAME”
- The proposal must be accompanied by Special Attachments No. 8 (“Tax Clearance Certificate”) and No. 10 (“Policy Regarding Sexual Harassment”). If you need a Tax Clearance Certificate, you can request one at https://www.ksrevenue.gov/taxclearance.html. Allow 2-3 business days for processing.
- The outline in Table 3 below describes the expected proposal organization and content sections.
- Table 4 lists the evaluation criteria and associated weights which will be used to make a selection.
Table 3: Proposal Content | |
---|---|
Section | Description of Intent |
Cover Letter | 1 page |
Project Approach | Demonstrate a unique approach to accomplish the design efficiently and to a high standard. Include cost-effective and optimized solutions to address the anticipated improvements in the design. Include unique qualifications or experience related to the project approach. |
Approach to Schedule | Describe the approach to accomplish the scope of services within the schedule requirements. Include anticipated key milestone dates and availability of staff. |
Approach to Quality Control | Describe methods or procedures your firm will use to provide all drawings, reports and other services with professional quality and technical accuracy. |
Qualifications and Experience | For key personnel to be assigned to the project provide names, office location, qualifications, education, training, and expertise. Identify their area(s) of responsibility and percent of their time dedicated to the project. List work for which you do not have in-house capability and name the firm you propose to subcontract with. |
Past Performance | Describe team’s past performance with respect to ability to meet project schedules; quality of work; and ability to control costs on similar transportation projects, especially those performed for KDOT. Include three references and contact information. |
Familiarity with KDOT and Project Area | Describe team’s familiarity with KDOT’s design process and standards. Describe familiarity with the project area and any identified special site conditions. |
Table 4: Evaluation Factors | |
---|---|
Evaluation Factor | Weight |
Qualifications and experience of project manager and other key project team members proposed for services | 20% |
Project approach | 25% |
Approach and commitment to meet advertised schedule | 10% |
Past performance history for similar projects/services for KDOT | 10% |
Understanding of the project area | 15% |
Demonstrated understanding of nature and scope of project | 20% |
Contract Terms and Conditions
A standard KDOT agreement for engineering and technical services will be used for professional services projects. The following special attachments will need to be provided by the selected consultant and all subconsultants with the signed work order following negotiations and will become attachments to the contract.
- Special Attachment No. 8 (“Tax Clearance Certificate”)
- Special Attachment No. 10 (“Policy Regarding Sexual Harassment”)
Questions
All questions regarding this request for proposals shall be emailed to KDOT.DesignContracts@ks.gov.
Questions can be submitted until May 26, 2022; answers will be provided to all prequalified consultants on June 2, 2022.
Marcia Turner, P.E., Contracts Manager
Division of Engineering and Design
Doc. No. 050155