Notice to Contractors

Electronic copies of the letting proposals and plans are available on the Kansas Department of Transportation (KDOT) website at https://kdotapp.ksdot.org/Proposal/Proposal.aspx. The website will allow the contractor to request approval from KDOT to bid as a prime contractor and be included on the “Bid Holders List,” or to be included on the “Non-Bid Holders List” as a subcontractor/supplier. KDOT’s approval is required to bid as a prime contractor. To bid as a prime contractor, KDOT needs to be notified of the intent to bid no later than the close of business on the Monday preceding the scheduled letting date. Failure to obtain prior approval to bid as a prime contractor on any projects listed below will be reason to reject your bid. The Secretary reserves the right to reject bids that do not comply with all requirements for preparing a bidding proposal as specified in the 2015 edition of the Kansas Department of Transportation Standard Specifications for State Road and Bridge Construction.

KDOT will only accept electronic internet proposals using the Bid Express website at http://www.bidx.com until 1:00 p.m. (CST) March 16, 2022. The KDOT bid letting will be conducted remotely by audio broadcast ONLY at 3:00 p.m. (CST) Wednesday, March 16, 2022. To join the conference call, dial 866-620-7326 and enter conference code 5895748207. KDOT has tested the process, but in the event of an unforeseen issue, KDOT will provide updates.

Each bidder shall certify that such person, firm, association, or corporation has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with the submitted bid. This certification shall be in the form of a required contract provision provided by the state to each prospective bidder. Failure to complete the required contract provision and certify the completeness of the preceding statement when electronically signing the proposal will make the bid nonresponsive and not eligible for award consideration.

District One – Northeast

Johnson – 56-46 KA-6246-01 – US-56, from the start of curbs in west Gardner northeast to N. Sycamore Street, milling and overlay, 0.9 mile. (Federal Funds)

Johnson – 56-46 KA-6370-01 – US-56, ramps at the US-56/I-35/W. 175th Street interchange to include unnamed road from southbound ramps to W. 175th Street in Gardner, overlay. (Federal Funds)

Pottawatomie – 75 TE-0501-01 – Green Valley Road, from US-24 to Eagles Landing Drive; pedestrian bridge located north of Elk Creek Road; and a crossing located at Hunter’s Drive, pedestrian and bicycle paths, 0.5 mile. (Federal Funds)

Shawnee – 70-89 KA-1266-06 – I-70 Polk/Quincy Viaduct from Topeka Boulevard to Kansas Avenue in Topeka, special, 0.3 mile. (Federal Funds)

Shawnee – 4-89 KA-6127-01 – K-4, bridge #231 over the Burlington, Northern and Santa Fe Railroad and the Shunganunga Creek located 0.71 mile north of the north US-40/K-4 junction, bridge repair. (Federal Funds)

Shawnee – 75-89 KA-6128-01 – US-75, bridges #206 and #207 over Topeka Boulevard (Old Highway 75) located 2.53 miles and 2.54 miles respectively, north of the Osage/Shawnee County line, bridge repair. (Federal Funds)

Shawnee – 4-89 KA-6244-01 – K-4, from the Wabaunsee/Shawnee County line to the K-4/I-70 junction, milling and overlay, 12.1 miles. (Federal Funds)

Shawnee – 24-89 KA-6393-01 – US-24, from 550 feet west of N.W. Rochester Road east to 1,130 feet east of N.W. Rochester Road in Topeka, milling and overlay, 0.3 mile. (Federal Funds)

Wabaunsee – 30-99 KA-6245-01 – K-30, from the K-30/I-70 junction to the city limits of Maple Hill, milling and overlay, 2.0 miles. (Federal Funds)

Wyandotte – 670-105 KA-5495-02 – I-670, approximately 580 feet east of the I-70/I-670 junction to approximately 634 feet west of the Wyandotte County/Missouri state line, lighting, 1.4 miles. (Federal Funds)

Wyandotte – 73-105 KA-5498-01 – US-73, US-73/K-7 junction and Hollingsworth Road on the Wyandotte/Leavenworth County line, intersection improvement. (Federal Funds)

Wyandotte – 70-105 KA-6086-01 – I-70, bridge #152 (over I-635 northbound) located at the I-70/I-635 Interchange, bridge redeck. (Federal Funds)

Wyandotte – 70-105 KA-6369-01 – I-70, from S. 78th Street east 4 miles to the west I-70/ I-635 interchange approach; from 0.5 mile east of the I-70 bridge over Kaw Drive east to the west S.18th Street bridge approach; and from the I-70/I-670 split east to the west Lewis and Clark Viaduct bridge, milling and overlay, 6.4 miles. (Federal Funds)

District Two – North Central

Dickinson – 70-21 KA-6406-01 – I-70, from approximately 1,843 feet east of the I-70/K-206 junction east to the Dickinson/Geary County line, patching and overlay, 2.9 miles. (Federal Funds)

Geary – 40B3-31 KA-3952-01 – US-40B3, bridge #035 (over the Union Pacific Railroad and Monroe Street) located approximately 1,214 feet east of US-77B in Junction City, bridge replacement. (Federal Funds)

Geary – 70-31 KA-6278-01 – I-70, from 0.64 mile east of the I-70/K-57 junction to the Geary/Riley County line, pavement patching, 15.5 miles. (Federal Funds)

Geary – 31 TE-0495-01 – 8th Street from Eisenhower Drive to Garfield Street, Garfield Street from 7th Street to 8th Street, and 7th Street from Garfield Street to K-57 highway in Junction City, pedestrian and bicycle paths, 0.5 mile. (Federal Funds)

Saline – 85 C-5061-01 – Simpson Road from Magnolia Road to Crawford Street, grading, 2.0 miles. (Federal Funds)

Saline – 143-85 KA-3940-01 – K-143, bridge #104 over the Saline River Drainage located 2.62 miles north of I-70 and bridge #103 over the Saline River Drainage located at the K-143/E. Granville Road intersection, bridge replacement. (Federal Funds)

District Three – Northwest

Graham – 283-33 KA-6418-01 – US-283, from Prout Street in Hill City to the Graham/Norton County line, milling and overlay, 13.5 miles. (Federal Funds)

Graham – 24-33 KA-6419-01 – US-24, from the east city limits of Hill City to the US-24/K-18 junction, milling and overlay, 8.2 miles. (Federal Funds)

Osborne – 181-71 KA-3938-01 – K-181, bridge #042 over Twin Creek located 6 miles south of US-24, bridge replacement. (Federal Funds)

Phillips – 36-74 KA-6002-01 – US-36, at 10 locations beginning 0.57 mile east of E. 300 Road east to 0.27 mile east of E. 1000 Road, guard fence, 6.7 miles. (Federal Funds)

Rooks – 82 K-1659-07 – From 1.83 miles south of the US-24/ Webster State Park Road entrance north to the US-24/Webster State Park Road entrance, state park road, 1.8 miles. (State Funds)

Rooks – 258-82 KA-6379-01 – K-258, from beginning of route to end of route at the US-24/K-258 junction, milling and overlay, 3.5 miles. (State Funds)

Russell – 281-84 KA-2370-03 – US-281, from Land Road north to the US-281/K-18 junction, grading and surfacing, 12.0 miles. (Federal Funds)

District Four – Southeast

Bourbon – 69-6 KA-5563-01 – US-69 and intersection of 3rd, 6th, 12th, and 25th Streets in Fort Scott, traffic signals, 2.0 miles. (Federal Funds)

Chautauqua – 166B-10 KA-4997-01 – US-166B, bridge #009 over Deer Creek, bridge replacement. (Federal Funds)

Cherokee – 11 KA-6371-01 – US-69 (Military Avenue), from the south city limits of Baxter Springs to the north city limits of Baxter Springs and US-166 (12th Street), from the west city limits of Baxter Springs east to the east city limits of Baxter Springs, milling and overlay, 4.4 miles. (State Funds)

Franklin – 68-30 KA-6329-01 – K-68, from the Franklin/Osage County line to the west city limits of Ottawa, milling and overlay, 12.3 miles. (Federal Funds)

Miami – 61 N-0709-01 – Metcalf Road from W. 287th Street to S. 2nd Street in Louisburg, grading and surfacing, 0.9 mile. (Federal Funds)

Osage – 68-70 KA-6328-01 – K-68, from the K-68/K-268 junction to the Osage/Franklin County line, milling and overlay, 1.0 mile. (State Funds)

District Five – South Central

Sedgwick – 87 N-0717-01 – Academy Avenue from S. Cathey Street to Maize Road in Maize, grading and surfacing, 0.6 mile. (Federal Funds)

District Six – Southwest

Meade – 54-60 KA-6130-01 – US-54, bridges #031 and #032 over Crooked Creek located 6.1 miles and 7.7 miles respectively, northeast of the US-54/ US-160 junction, bridge repair. (Federal Funds)

Julie Lorenz
Secretary