Government Website icon

The .gov means it's official.
A .gov website belongs to an official government organization in the United States.

Padlock icon

The site is secure.
The https:// or lock icon ensures you're safely connected to the website and any information you provide is encrypted.

Publications iconKansas Register

Volume 41 - Issue 3 - January 20, 2022

State of Kansas

Department of Transportation

Notice to Consulting Firms

The Kansas Department of Transportation (KDOT) is seeking a qualified consulting firm or team of firms to perform professional services for the project(s) described in Table 1 below. Interested consultants must email a letter of interest to KDOT.DesignContracts@ks.gov by 12:00 p.m. (CST) February 4, 2022, to be considered for selection.

Consultant Prequalification

Interested consulting firms must be prequalified by KDOT or otherwise demonstrate qualification in the following Categories: 211 Highway Design–Major Facility; 221 Non-Standard Span Bridge Design; 231 Traffic Control Analysis and Design; 301 Land Surveying; 302 Engineering Surveying; 336 Right of Way Services; and 401 Landscape Seeding and Erosion Control.

If a firm is not currently prequalified by KDOT, a proposal may still be submitted. Firms not prequalified must also provide documentation that demonstrates the firm is qualified for each specified category listed in this notice for the project. Firms must use the KDOT prequalification form to provide this documentation. KDOT 1050 Prequalification category definitions (Blue Book) can be found at http://www.ksdot.org/descons.asp. Consultants may create a team to meet the prequalification requirements. All firms doing business with KDOT must be registered and in good standing under the laws of the State of Kansas at the time of contracting and must comply with applicable state and federal laws, rules, and regulations.

Table 1: Background and Scope of Project
Project Number Background and Scope of Project
KA-6517-01 This project is the replacement of the I-135 bridge (BR# 87(305)) which carries traffic from southbound I-135 to eastbound US-54 in Sedgwick County. This structure is a single lane ramp “flyover” bridge.

Table 2: Project Summary
Project Number Route-County and Scope Length Project Termini
KA-6517-01 I135-087
Bridge Replacement
N/A N/A
Project Number Structures BR#, Structure Scope, Structure Size and Type
KA-6517-01 Bridge #305
Bridge Replacement; Length: +/-946.4 feet, Roadway Width: 30 feet; Existing structure is a curved, super-elevated box RCBG with hinges

Anticipated Consultant Scope

KDOT anticipates the following to be included in the consultant’s scope: Survey services; preliminary design services; final design services; environmental documentation preparation (permitting); 3D electronic deliverables preparation; right of way services; and letting and construction phase services.

Services associated with this request for proposals begin at preliminary design and continue through final design. No discovery phase services will be required.

Current expectations for consultant scope and what will be provided by KDOT are detailed below. The scope included herein may not be all-inclusive. A scoping meeting will take place after consultant selection is made.

Project Management

  • Develop and communicate project management plan and quality assurance plan.
  • Perform quality control checks according to quality assurance plan.
  • Provide electronic plan files compliant with KDOT Graphic Standards Manual, including CAD conformance checks and ControlCAD indexed DGN files with ProjectWise attributes.
  • Provide construction cost estimates at major project milestones.

Survey and Right of Way

  • Provide a full survey including structures in the existing right of way. The deliverables shall incorporate the full project including the roadway and bridge surveys and will be provided in the Kansas Regional Coordinate System.
  • Determine impacts to right of way and utilities.
  • Based upon consultant’s field survey data and historical KDOT project information, consultant shall establish and compile into a right of way strip map the positions and locations of the existing highway right of way and property lines for the ownership adjacent thereto. Consultant shall perform these activities using coordinate geometry and Bentley Open Site Designer.

Road Design

  • Develop plans to materials and research.
  • Develop preliminary plans to field check.
  • Develop office check plans.
  • Develop final plans for construction.
  • Perform roadway geometric design, drainage design, and roadside safety analysis.
  • Visit the project site location.

Bridge Design

  • The consultant shall propose and evaluate different framing layouts for review and acceptance by the KDOT Bridge office. Focus shall be to minimize disruption to the site and facilitate efficient construction to minimize closure of southbound I-135 ramp to eastbound US-54.
  • The proposed structure will need to match or improve the existing structure’s geometry (vertical profile, horizontal, and cross-slope). The proposed structure will need to provide vertical clearance windows for I-135 below, according to current standards.
  • Develop preliminary plans to pre-field check (contour map, construction layout(s) and typical Section (S)).
  • Develop preliminary plans to field check.
  • Develop pre-office check plans (bridge structural details and load rating model).
  • Develop office check plans.
  • Develop final plans for construction.

Traffic Engineering

  • Development of traffic management plan, including coordination with the local government and KDOT Metro office.
  • Develop permanent signing and pavement marking plans.
  • Develop traffic control plans.

Transportation Planning

  • Determine present and future traffic projections for adjacent interchanges using the current WAMPO travel demand model.
  • Estimate truck traffic using the WAMPO travel demand model and KDOT’s traffic flow maps.
  • Coordinate information with the Transportation Planning Forecasting Group.

Activities to be performed by KDOT include:

  • Environmental services, including lead paint and asbestos testing and permit application.
    • Note: Technical data to support these activities will be required from the consultant immediately after field check.
  • Utility coordination, if required.
  • Geotechnical services including soil investigations, bridge foundation geology, pavement field investigation and design, and surfacing recommendations.

Anticipated Schedule and Key Dates

  1. Proposals are due by or before 12:00 p.m. (CST) February 4, 2022
  2. The program fiscal year for this project is FY 2026 (July 2026–June 2027)
  3. Other important dates:
    1. Survey Complete: July 28, 2022
    2. Plans to Materials and Research: December 30, 2022
    3. Field Check: October 2, 2023
    4. Plans to Right-of-Way: November 14, 2023
    5. Plans Complete: May 19, 2025

Instructions for Proposal

  1. No cost or pricing information shall be submitted with the proposal. Proposals including cost or pricing information will be considered non-responsive and withdrawn from further consideration.
  2. The consultant’s proposal must not exceed 6 pages total (including any cover letter, index, etc.)
  3. A PDF (2MB maximum size) of the proposal must be emailed to KDOT.DesignContracts@ks.gov by the proposal due date and time.
  4. The subject line of the email and the PDF file name must read:
    1. “KA-6517-01–Replace BR305 on I-135 in Sedgwick Co_FIRM NAME”
  5. The proposal must be accompanied by Special Attachments No. 8 (“Tax Clearance Certificate”) and No. 10 (“Policy Regarding Sexual Harassment”). If you need a Tax Clearance Certificate, you can request one at https://www.ksrevenue.gov/taxclearance.html. Allow 2-3 business days for processing.
  6. The outline in Table 3 below describes the expected proposal organization and content sections.
  7. Table 4 lists the evaluation criteria and associated weights which will be used to make a selection.

Table 3: Proposal Content
Section Description of Intent
Cover Letter 1 page
Project Approach Demonstrate a unique approach to accomplish the design efficiently and to a high standard. Include cost-effective and optimized solutions to address the anticipated improvements in the design. Include unique qualifications or experience related to the project approach.
Approach to Schedule Describe the approach to accomplish the scope of services within the schedule requirements. Include anticipated key milestone dates and availability of staff.
Approach to Quality Control Describe methods or procedures your firm will use to provide all drawings, reports and other services with professional quality and technical accuracy.
Qualifications and Experience For key personnel to be assigned to the project provide names, office location, qualifications, education, training, and expertise. Identify their area(s) of responsibility and percent of their time dedicated to the project. List work for which you do not have in-house capability and name the firm you propose to subcontract with.
Past Performance Describe team’s past performance with respect to ability to meet project schedules; quality of work; and ability to control costs on similar transportation projects, especially those performed for KDOT. Include three references and contact information.
Familiarity with KDOT and Project Area Describe team’s familiarity with KDOT’s design process and standards. Describe familiarity with the project area and any identified special site conditions.

Table 4: Evaluation Factors
Evaluation Factor Weight
Qualifications and experience of project manager and other key project team members proposed for services 20%
Past performance history for similar projects/services for KDOT 20%
Commitment to meet advertised schedule 10%
Approach to quality control 10%
Understanding of the project area 10%
Demonstrated understanding of nature and scope of project 30%

Contract Terms and Conditions

A standard KDOT agreement for engineering and technical services will be used for professional services projects. The following special attachments will need to be provided by the selected consultant and all subconsultants with the signed work order following negotiations and will become attachments to the contract.

  • Special Attachment No. 8 (“Tax Clearance Certificate”)
  • Special Attachment No. 10 (“Policy Regarding Sexual Harassment”)

Questions

All questions regarding this request for proposals shall be emailed to KDOT.DesignContracts@ks.gov.

Questions can be submitted until January 28, 2022; answers will be provided to all prequalified consultants on January 31, 2022.

Marcia Turner, P.E., Contracts Manager
Division of Engineering and Design

Doc. No. 049757